Project Name | Location | Length (km) | Carriage way (m) | Date of Commencement | Date of Completion | Description | Progress as at 30 June 2020 | |
C1 | Kandy – Kirimatiya Road | Central and Uva Province | 7.64 km | 9.5 | 29 Nov. 2018 | 28 Nov. 2020 | Ongoing | 62% |
Ampitiya – Gurudeniya (Pichchamalwatta) Road | 2.25 km | 9.5 | 29 Nov. 2018 | 28 Nov. 2020 | ||||
Nuwara Eliya – Ragala – Udapussellawa Road | 27 km | 9.1 | 29 Nov. 2018 | 28 Nov. 2020 | ||||
Welimada – Kirkless Road | 17.83 km | 9.1 | 29 Nov. 2018 | 28 Nov. 2020 | ||||
Avissawella - Hatton – Nuwara Eliya Road | 9.59 km | 8.9 | 29 Nov. 2018 | 28 Nov. 2020 | ||||
C2 | Reconstruction of Bridge Nos. 24/3 and 42/1 on Tennakumbura – Rikillagaskada – Ragala Road | 2 Nos. | 8.6 | 29 Nov. 2018 | 28 May 2020 | Ongoing | 73% | |
Reconstruction of Bridge No. 3/2 on Kandy – Kirimatiya Road | 1 No. | 8 | 29 Nov. 2018 | 28 May 2020 | ||||
Reconstruction of Bridge Nos. 23/3, 27/2, 30/4, 31/5, 34/8, 37/1 and 38/5 on Nuwara Eliya – Ragala – Udapussellawa Road | 7 Nos. | 7.6 | 29 Nov. 2018 | 28 May 2020 | ||||
Reconstruction of Bridge Nos. 1/1, 2/5, and 7/7 on Welimada – Kirkless Road | 3 Nos. | 7.6 | 29 Nov. 2018 | 28 May 2020 |
![]() |
![]() |
![]() |
![]() |
|
Kandy – Kirimatiya Road (B195) Drain Construction |
Kandy – Kirimatiya Road (B195) Sub Grade Preparation |
Ampitiya Gurudeniya Road Asphalt Completed Section |
Ampitiya Gurudeniya Road Sub grade Preparation |
|
![]() |
![]() |
![]() |
![]() |
|
Nuwara Eliya – Ragala – Udapussellawa Road Priming Work |
Nuwara Eliya – Ragala – Udapussellawa Road Culvert Construction |
Welimada – Kirklees Road Wearing Course laying |
Welimada – Kirklees Road Wearing course laying section |
|
![]() |
![]() |
![]() |
![]() |
|
Avissawella – Hatton – Nuwara Eliya Road Drain Construction Work |
Avissawella – Hatton – Nuwara Eliya Road Sub Grade Preparation | Tennakumbura – Rikillagaskada – Ragala Road, Bridge Construction (24/3 Bridge) | Tennakumbura – Rikillagaskada – Ragala Road, Bridge Construction (42/1 Bridge) | |
![]() |
![]() |
![]() |
![]() |
|
Reconstruction of Bridge on Nuwara Eliya – Ragala – Udapussellawa Road Bridge Construction (27/2 Bridge) |
Reconstruction of Bridge on Nuwara Eliya – Ragala – Udapussellawa Road Bridge Construction (27/2 Bridge) |
Reconstruction of Bridge on Welimada – Kirklees Road Bridge Construction (7/7Bridge) |
Reconstruction of Bridge on Welimada – Kirklees Road Bridge Construction (2/5 Bridge) |
|
Designation | Name | Telephone | Fax | |
---|---|---|---|---|
Project Director | Mr. M.R.Sudath | 011 2877716 | 011 2862928 | This email address is being protected from spambots. You need JavaScript enabled to view it. |
Engineer | Mrs. G.T. Dananjani | 011 2862896 | 011 2862928 | |
Engineer | Mr.R.H.G.I.K. Chamara | 011 2862896 | 011 2862928 | |
Accountant | Mrs. Shyama Neelamanee | 011 2877729 | 011 2883069 | This email address is being protected from spambots. You need JavaScript enabled to view it. |
Administrative Assistant | Mr. A. P.C.A. Jayamal | 011 2886110 | 011 2883069 | This email address is being protected from spambots. You need JavaScript enabled to view it. |
Office (Gen.) | - | 011 2862928 | 011 2862928 | This email address is being protected from spambots. You need JavaScript enabled to view it. |