Project Monitoring Unit | : | Port Access Elevated Highway Project |
Funding Agency | : | Asian Development Bank (ADB) |
Project Type | Length (km) | Commence. Date | Description | Progress as at 30/09/2023 |
PAEH - CW - 01 | 5.3 | Sep - 19 | Construction of Port Access Elevated Highway | 94.00 |
PAEH - CW - 02 | Jul - 21 | Construction of Maritime Facilitation Center (Building) | 44.50 | |
PAEH - CW - 03 | Jun - 19 | Pilling works for Maritime Facilitation Center (Pilling) | 100.00 | |
PAEH - EQ - 1 | Sep - 23 | Construction of Connecting Roads of PAEH/Ramps | - | |
PAEH - CO - CSC | Sep - 19 | Construction Supervision of PAEH | N/A | |
PAEH - CO - ETC | Oct - 21 | Procurement of Consultant for Electronic toll Collection System Management | N/A | |
PAEH - IC - 01 | Jan - 21 | Individual Consultant - Structural Advisor | N/A | |
PAEH - IC - 03 | Jan - 21 | Individual Consultant - Contract Engineer | N/A | |
Jun - 19 | Design of Building & Construction Supervision of Port Building | N/A |