Name of the Project Road (Section / Bridge No) |
Project Type |
Funding Agency |
Location |
Length of the
Bridge(m) |
Width
Bridge(m) |
Commencement Date |
Target Completion Date |
Description |
Physical Progress as at 30th June 2020 |
Construction of bridge nos. 53/1 & 53/2 on Colombo-Ratnapura-Wellawaya - Batticaloa (A004) Road (CRIP/WORKS/RDA/NCB/304) |
Foreign Aid Loan |
World Bank |
Bridge Nos. 53/1 & 53/2 |
420m |
24m |
08.02.2017 |
07.02.2018 |
Decided to go for mutual termination due to delay in land acquisition. The objective of flood prevention has been achieved by improving flow of 53/5 Bridge |
29% |
Rectification of Land Slide Between Culvert No 75/5 to 76/4 on Peradeniya - Badulla - Chenkaladi Road (A005) Road (CRIP/WORKS/RDA/NCB/308) |
Foreign Aid Loan |
World Bank |
Culvert No 75/5 to 76/4 |
- |
- |
25.05.2017 |
31.08.2020 |
Delay due to slow progress of the contractor and rainy weather, covid 19 |
93.50% |
Re- Construction of Bridge No. 23/1 on Warakapola - Ruwanwella Road (B457) (CRIP/WORKS/RDA/NCB/318) |
Foreign Aid Loan |
World Bank |
Bridge No. 23/1 |
240m |
10.4m |
21.06.2017 |
19.11.2020 |
Delayed due to slow Progress of the Contractor,land Acquisition, inclement weather , covid 19 |
76.66% |
Construction of New Bridge at CH 15+500,at Thalwila Estuary on Nainamadama -Iranawila-Chilaw (B640) Road (CRIP/WORKS/RDA/NCB/320) |
Foreign Aid Loan |
World Bank |
Bridge at CH 15+500,at Thalwila Estuary |
80m Bridge & 100m approach on either sides |
10.4m |
27.03.2019 |
30.11.2020 |
Work in progress |
71% |
Design and Construction of Rock fall Protection Works Between Culvert Nos. 41/9 and 41/10, between 50th km and Culvert No.51/1 & between Culvert Nos. 55/3 and 55/6 on Kandy -Mahiyanginuyu Road (A026) (CRIP/WORKS/RDA/NCB/321) |
Foreign Aid Loan |
World Bank |
Culvert Nos. 41/9 and 41/10, between 50th km and Culvert No.51/1 & between Culvert Nos. 55/3 and 55/6 |
- |
- |
03.07.2019 |
30.10.2020 |
Work in progress |
51% |
Supply and installation of Instruments in Land Slide areas in A026, A004, A005 & A007 Roads (CRIP/WORKS/RDA/NCB/323) |
Foreign Aid Loan |
World Bank |
Land Slide areas in A026, A004, A005 & A007 Roads |
- |
- |
19.06.2019 |
30.09.2020 |
Work in progress |
60% |
Re-Construction of Bridge No. 60/5 on Thiruwanketiya - Agalawatta (B421)Road (CRIP/WORKS/RDA/NCB/325) |
Foreign Aid Loan |
World Bank |
Bridge No.60/5 |
150m |
10.4m |
20.09.2019 |
21.10.2020 |
Work in progress |
63% |
i) Re-Construction of Bridge No. 98/4 on Colombo- Ratnapura - Wellawaya - Batticaloa (A004) Road
ii) Re-Construction of bridge at ch. 0+480 km on Ehaliyagoda Bypass Road (CRIP/WORKS/RDA/NCB/326) |
Foreign Aid Loan |
World Bank |
Bridge No. 98/4 Bridge & 0+480km on Ehaliyagoda Bypass Road |
i) 80m
ii) 150m |
i) 12.4m
ii) 16m |
18.10.2019 |
30.11.2020 |
Work in progress |
48.89% |
Construction of a New Bridge by replacing existing causeway No. 1/2 on Sri Baritheendra Mawatha (B397(h)) across Malwathu oya, Anuradhapura (CRIP/WORKS/RDA/NCB/327) |
Foreign Aid Loan |
World Bank |
Causeway No. 1/2 on Sri Baritheendra Mawatha (B397(h)) across Malwathu oya, Anuradhapura |
1150m |
9.80m |
09.10.2019 |
15.12.2020 |
Work in progress |
65% |
Re-Construction of 02 Nos Bridges [ 6/1, 6/3 on KRW B168 RD.] on National Highways In Gampaha Chief Engineer’s Region (CRIP/WORKS/RDA/NCB/329) |
Foreign Aid Loan |
World Bank |
Bridge No. 6/1 and Bridge No. 6/3 |
120m |
10.4m |
15.05.2020 |
14.10.2020 |
Delayed due to late Mobilization of the Contractor and submission of documents to sign Contract. |
2.00% |
Re-Construction of 03 Nos Bridges [2/3 PH B354 rd., 6/1 MI B285 rd., 3/3 KN B207 rd.] on National Highways in Colombo & Kaluthara Chief Engineer’s Region (CRIP/WORKS/RDA/NCB/330) |
Foreign Aid Loan |
World Bank |
Bridge No. 2/3 & Bridge No. 6/1 & Bridge No. 3/3 |
250m |
10.4m |
18.05.2020 |
17.10.2020 |
Work in progress |
22% |
Re-construction of 02 nos. bridges [31/2, 15/3 ] on Paranthan - Mulativu - Knochchi Road in Mulativu Chief Engineer’s Region (CRIP/WORKS/RDA/NCB/333) |
Foreign Aid Loan |
World Bank |
Bridge No. 31/2 and Bridge No 15/3 |
100m |
10.4m |
05.05.2020 |
04.10.2020 |
Work in progress |
20% |
Re-construction of Bridge No. 18/1 & Bridge No.18/2 on Nawalapitiya - Dolosbage (B 318) Road in Kandy Chief Engineer’s Region (CRIP/WORKS/RDA/NCB/334) |
Foreign Aid Loan |
World Bank |
Bridge No. 18/1 & 18/2 |
100m |
8.5m |
26.05.2020 |
05.11.2020 |
Work in progress |
3% |