C38 VO – Debathgama – Kalugala Road Completed Section |
C38 VO – Debathgama – Kalugala Road
Completed Section |
C39 VO – Kannaththota – Ihalagama Road
Asphalt complete section |
C39 VO – Kannaththota – Ihalagama Road
Asphalt complete section |
|
|
|
|
|
|
Progress as at 30 June 2019 |
|
|
|
|
|
|
|
|
C40 VO – Improvement of Bulathkohupitiya Town
Prime laying |
C40 VO – Improvement of Bulathkohupitiya Town
Sub Grade Preparation |
C41 VO – Improvement of Mawanella Town
ABC Work |
C41 VO – Improvement of Mawanella Town
Asphalt Laying |
|