EXIM Bank Funded Hunan Project
 
     
  PMU Name : EXIM Bank Funded widening and Improvement of 64.31 km Road and Reconstruction of 13 Bridges in Central and Uva Provinces  
  Funded By : China Development Bank  
 
Project Name
Location
Length (km)
Carriage way (m)
Date of Commencement
Date of Completion
Description
Progress as at
30 June 2020
C1 Kandy – Kirimatiya Road Central and Uva Province 7.64 km 9.5 29 Nov. 2018 28 Nov. 2020 Ongoing 62%
Ampitiya – Gurudeniya (Pichchamalwatta) Road 2.25 km 9.5
Nuwara Eliya – Ragala – Udapussellawa Road 27 km 9.1
Welimada – Kirkless Road 17.83 km 9.1
Avissawella - Hatton – Nuwara Eliya Road 9.59 km 8.9
C2 Reconstruction of Bridge Nos. 24/3 and 42/1 on Tennakumbura – Rikillagaskada – Ragala Road 2 Nos. 8.6 29 Nov. 2018 28 May 2020 Ongoing 73%
Reconstruction of Bridge No. 3/2 on Kandy – Kirimatiya Road 1 No. 8
Reconstruction of Bridge Nos. 23/3, 27/2, 30/4, 31/5, 34/8, 37/1 and 38/5 on Nuwara Eliya – Ragala – Udapussellawa Road 7 Nos. 7.6
Reconstruction of Bridge Nos. 1/1, 2/5, and 7/7 on Welimada – Kirkless Road 3 Nos. 7.6
 
     
  Project Photographs  
 
 
Kandy – Kirimatiya Road (B195)
Drain Construction
Kandy – Kirimatiya Road (B195)
Sub Grade Preparation
Ampitiya Gurudeniya Road
Asphalt Completed Section
Ampitiya Gurudeniya Road
Sub grade Preparation
 
 
Nuwara Eliya – Ragala – Udapussellawa Road
Priming Work
Nuwara Eliya – Ragala – Udapussellawa Road
Culvert Construction
Welimada – Kirklees Road
Wearing Course laying
Welimada – Kirklees Road
Wearing course laying section
 
 
Avissawella – Hatton – Nuwara Eliya Road
Drain Construction Work
Avissawella – Hatton – Nuwara Eliya Road Sub Grade Preparation Tennakumbura – Rikillagaskada – Ragala Road, Bridge Construction (24/3 Bridge) Tennakumbura – Rikillagaskada – Ragala Road, Bridge Construction (42/1 Bridge)  
 
Reconstruction of Bridge on Nuwara Eliya – Ragala – Udapussellawa Road
Bridge Construction (27/2 Bridge)
Reconstruction of Bridge on Nuwara Eliya – Ragala – Udapussellawa Road
Bridge Construction (27/2 Bridge)
Reconstruction of Bridge on Welimada – Kirklees Road
Bridge Construction (7/7Bridge)
Reconstruction of Bridge on Welimada – Kirklees Road
Bridge Construction (2/5 Bridge)
 
         
 
 