Extension of Southern Expressway Project (ESEP) - Section 4 (Hambanthota to Mattala via Andarawewa)
 
  

Funded By: Exim Bank of China & GOSL

Location / Road
Length
Width
Commencement
date
Target Completion Date
Physical Progress
as at 07 Nov. 2019
Description
Mattala to Hambantota via Andarawewa (Section 4)
25 km (Approximately)
Initial outer 4 lane expressway comprises of each 3.6m wide lanes, 2.5m wide outer hard shoulder, 0.75m wide inner hard shoulder and 0.75m verge on either side with 2.0m wide center median. Construction of embankments, cutting and sub structures of bridges, viaducts etc. where 6 lane facilities is required in future, will be with the provision for expanding to 6 lanes.
19 Jan. 2016
09 July 2019
Completed
Scope of Works
1. No. of Viaducts: 02 No.s (0.87 km)
2. No. of Interchanges: 01 No.s
3. No. of Bridges: 06 No.s
4. No. of Bridge Underpasses: 02 No.s
5. No. of Overpasses: 02 No.s
6. No. of Culvert Underpasses : 10 No.s
7. No. of Box Culverts :- 61 No.s
8. No. of Aqueduct :- 01 No.
9. Cut length :- 4.17 km
10. Fill length :- 19.58 km
 
 
 
Progress Photographs
           
Progress as at 30th September 2019 - Andarawewa Interchange Area
 
 
  Arabokka Junction Arabokka Toll Gate Area BRO-01 Overpass Bridge CH 1+280 CH 2+100 to CH 2+600  
 
 
  CH 12+250 to CH 13+000 CH 14+000 Andarawewa System Interchange Area Mattala Toll Gate Area  
 
Progress as at 30th June 2019 - Andarawewa Interchange Area
 
 
           
Progress as at 31st December 2018
 
 
 
Highway Construction Work
Andarawewa Interchange Area Construction Interchange Bridge
BRI-01 C1+506 to C1+656
Bridge
BR-01 CH 2+710 to CH 2+890
 
           
 
 
  Overpass Bridge
BRO-01 CH 1+280
Overpass Bridge
BRO-02 CH 2+072
Viaduct 01
CH 75+004 to CH 75+634
Viaduct 02
CH 76+140 to CH 76+380