Progress as at 31st December 2019 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Progress as at 30th September 2019 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Progress as at 30th June 2019 |
|
|
|
|
|
|
|
Road Pavement and Sign Board CH57+800 |
Road Pavement and Sign Board CH67+300 |
|
|
|
|
Progress as at 31st December 2018 |
|
|
|
|
|
|
|
ACH0+100-ACH0+400 Subgrade Filling (Wetiya) |
CH56+403 Underpass Backfill |
CH57+000-CH57+600 Binder Course Completed |
CH57+300-CH57+600 Slope Cutting |
CH58+000-CH59+000 Subbase Construction |
|
|
|
|
|
|
|
|
|
|
|
|
|
CH60+295 Walawe Bridge Completed |
CH60+600-CH60+800 Base Course Construction |
CH62+997 Bridge Parapet Wall Construction |
Laying of Asphalt concrete binder course at CH. (61+360-61+568) |
Commencement of Road work of other Major Roads (HR-6, HR-10 & HR-21) |
|
|
|
|
|
|
|
|
|
|
|
|
|
CH68+300-CH68+700 Guardrail Construction |
Sooriyawewa Toll Buildings Foundation construction |
|
|
|
|
Progress as at
30th September 2018 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|