Badulla Chenkaladi Road Improvement Project
 
 
Funding Agency : Opec Fund for International Development (OFID) & Saudi Fund for Development (SFD)  
                   

Project Name

Type

Funding Agency Location

Length

Width

Commencement
Date

Target
Completion Date

Description

Progress
as at 30 June 2020

Badulla Chenkaladi Road Improvement Project (BCRIP)
Foreign Funded Rehabilitation & Improvement
OPEC Fund for International Development - (OFID) US$ 60 Mn
Component B Badulla to Bibile (130+800km to 190+800km)
60 km
8.5 m
12.01.2017 * 1st Extension
23.06.2020
  • Contract Package -OFID/01 Badulla to Passara (130+800km to 150+800 km) International Contruction Consortium (Pvt) Ltd.
87.03%
12.01.2017 * 1st Extension 26.12.2019
  • Contract Package -OFID/02 Passara to Lunugala (150+800 km to 171+800 km) VVk-AMSK Joint Venture.
68.00 %
26.07.2017 * 1st Extension 16.02.2020
  • Contract Package -OFID/03 Lunugala to Bibile (171+800km to 190+800 km) K.D.Ebert & Sons Holding (Pvt) Ltd.
41.00 %
Saudi Fund for Development - (SFD) US$ 60 Mn )
Component A Bibile to Chenkaladi (190+800km to 277+550km) 86.75 km 18.07.2018 17.01.2021
  • Contract Package -SFD/01
    Bibile to Padiyathalawe (190+800km to 219+800 km) Consulting Engineers & Contractors
64.84%
18.07.2018 17.01.2021
  • Contract Package -SFD/02 Padiyathalawe tp Tampitiya (219+800km to 249+800 km) Consulting Engineers & Contractors
59.10 %
22.10.2018 21.04.2021
  • Contract Package -SFD/03 Tampitiya to Chenakaladi (249+800km to 277+800 km) Maga Engineering (Pvt) Ltd.
67.47%
              * Evaluating EOT Claim

 

 
 
OFID Section
 
SFD Section
 
Click on the image to view a large preview.   Click on the image to view a large preview.
 
  Project Progress Photographs:  
 
       
Asphalt Wearing Course Paving Prime Coat Surfacing Work Primed area CH 205+530km Reinforcement for - Culverts
Wing Wall Base Construction Interlock Paving Foot Walk @ Muthiyangana Temple - Premises - OFID Package 01 Turffing Work at Protection Area - OFID Package 01 ABC Laying - OFID Package 02
 
Asphalt Laying - OFID Package 02 ABC Over Laying - OFID Package 03 Formwork and Reinforcement Work of Line Drain - OFID Package 03  
 
 
Last modified date: 04-Aug-2020